Where NSW's data centre projects stand in November

Two NSW data centre approvals and four proposals we have covered, from Huntingwood to Kurri Kurri, with where each sits in the state assessment process.

Illustration for: Where NSW's data centre projects stand in November
2approved
4proposed
96MWHuntingwood and Wyong each

Six New South Wales data centre projects have crossed our desk since mid-October. Two have state approval. Four are proposals that have not been decided. This is where each one stands, drawn only from our earlier reporting.

Why it matters

Every one of these is a state significant development, so the decision sits with the NSW Department of Planning, Housing and Infrastructure, not the local council. Councils can object, and several have, but the record we have read shows an objection has not on its own stopped a consent. For landowners and contractors, the useful question is which stage a project has reached, because only approved schemes have conditions to price.

The news that moved today. Free email. Every weekday morning.

The numbers

Approved

  • Microsoft’s Huntingwood data centre at 6 Honeman Close was approved on 1 October 2026 (SSD-58601963). The reported cost is $1.263 billion and the IT load is 96MW. Blacktown City Council objected over conservation land, and the consent clears 0.31 hectares of Cumberland Plain Woodland with offsets and a covenant.
  • Goodman’s Project Apollo at Macquarie Park won state approval on 2 September, according to our report on its 2,150-home plan across the road. The data centre is reported at $1.4 billion and 135MW. Goodman’s towers, by contrast, still await a ministerial call on whether to declare them state significant.

Proposed

  • NEXTDC’s Horsley Park expansion (SSD-108864209) is on exhibition. The reporting gives its cost as either $1.79 billion or $3.50 billion, so neither figure should be treated as confirmed.
  • DCG Admin’s Lucca Road scheme at Wyong is a 96MW proposal at the scoping stage (SSD-148199991). The $1.5 billion figure comes from the Newcastle Herald, not the planning record.
  • The $3.7 billion Kurri Kurri project (SSD-128819490), rated at 550.5MW, was exhibited from 14 October to 11 November 2026. Cessnock council voted unanimously to object, and residents say AirTrunk’s $37 million benefits package is conditional on approval.
  • CDC’s Gregadoo campus near Wagga Wagga is the largest: a proposed $15 billion, 1.4GW, four-building scheme at the scoping stage, with two petitions running.

We have not summed these costs. Several are outlet-reported, and the NEXTDC figure is in dispute.

What’s next

Watch three things. First, the state’s assessment of Kurri Kurri now that submissions have closed; no decision date has been reported. Second, whether the Horsley Park cost figures are settled by NEXTDC or the portal. Third, whether Wyong and Gregadoo move from scoping to a full environmental impact statement. Nothing here should be read as approval until the portal shows a determination.

Quick answers

What is the latest on Microsoft?

Two NSW data centre approvals and four proposals we have covered, from Huntingwood to Kurri Kurri, with where each sits in the state assessment process.

What are the key numbers in this story?

approved: 2; proposed: 4; Huntingwood and Wyong each: 96MW.

Where does this information come from?

This story cites NSW Planning Portal, Honeman Close data centre, NSW Planning Portal, Kurri Kurri data centre and Mingtiandi, including the public record (NSW Planning Portal, Honeman Close data centre and NSW Planning Portal, Kurri Kurri data centre). Every source is linked on the page.

On the record

Our own coverage since 13 October tracks six NSW data centre projects: two approved by the state and four proposed or at the scoping stage.

Our coverage · Read our earlier story

Primary record

How we report →

Filed by the AusDev Sydney Desk. How we report.