671 of 759 submissions oppose AirTrunk's Kurri Kurri data centre
Exhibition of AirTrunk's Loxford data centre closed on 11 November with 671 objections and 77 in support, with the decision resting with the NSW Government.

- Source Briefing
- Read original source · Newcastle Weekly
The public exhibition period for AirTrunk’s proposed data centre at Loxford, near Kurri Kurri in New South Wales, closed on Wednesday 11 November with 671 of 759 submissions objecting, according to the Newcastle Herald and Newcastle Weekly.
Why it matters
The Herald reported that 77 submissions supported the $3.7 billion proposal and a further 11 offered comment. The 671 objections are about 88 per cent of the total, and the three categories add up to the 759 reported.
The news that moved today. Free email. Every weekday morning.
Newcastle Weekly said the NSW Planning Portal shows those counts, citing residents group Residents Against Datacentres In Kurri Kurri And Loxford (RADIKKAL). The Herald gave the same totals.
RADIKKAL spokesperson Graeme Davies said residents had given AirTrunk the same answer at its drop-in sessions, in its survey and now in submissions to the department. “The minister now has 671 reasons to refuse it,” he said.
RADIKKAL also says 82 per cent of respondents to AirTrunk’s own community survey did not want the project. Separately, the Herald quoted a submitter who cited the survey tally as 424 opposed and 65 in support.
This follows our earlier report on the council objection and the $37 million benefits package. In October Cessnock City Council unanimously resolved to object formally, Newcastle Weekly reported, pointing to noise, traffic, power demand and how close the site is to homes.
The numbers
Both outlets describe a proposed 540-megawatt data centre on Hart Road, Loxford. Newcastle Weekly places it on the former Hydro Aluminium smelter site.
Newcastle Weekly reported that AirTrunk puts the nearest home more than 500 metres from the facility. RADIKKAL, quoted by both outlets, says residents live 600 metres from 312 chillers on a 16-metre gantry. These are the company’s and the objectors’ own descriptions.
Per Newcastle Weekly, AirTrunk values its proposed community benefits package at more than $37 million. The company also claims over 350 ongoing jobs and no use of the community water supply for cooling.
Submitters quoted by the Herald raised noise, power costs, consultation and jobs estimates. Supporters pointed to employment and the site’s industrial history. One supporter asked for the $37 million community fund to be a binding condition. The Hunter Region Business Enterprise Centre supported it, with the condition that any approval carries enforceable measures to cut town water use.
What’s next
Because it is a State Significant Development, the final decision rests with the NSW Government rather than Cessnock City Council, Newcastle Weekly reported. Neither outlet gave a decision date.
RADIKKAL has asked the Department of Planning, Housing and Infrastructure to send the application to the Independent Planning Commission for a hearing, order an independent low-frequency noise study at the nearest homes, and recommend refusal. The group says 671 objections is far above a 100-objection trigger for IPC referral. That trigger is the group’s claim, not something either outlet confirmed.
Quick answers
What is the latest on AirTrunk?
Exhibition of AirTrunk's Loxford data centre closed on 11 November with 671 objections and 77 in support, with the decision resting with the NSW Government.
What are the key numbers in this story?
objections: 671; submissions: 759; capacity: 540MW.
Where does this information come from?
This story cites Newcastle Weekly and Newcastle Herald. Every source is linked on the page.
Sources
Also reported by
- Newcastle WeeklyKurri Kurri data centre draws 671 objections as submissions close
- Newcastle HeraldKurri Kurri data centre plan hit by 671 formal objections
Filed by the AusDev Sydney Desk. How we report.