Wyong data centre: 96MW proposed for Lucca Road, North Wyong
A 96MW data centre at Lucca Road, Wyong is listed as state significant development SSD-148199991 at the SEARs stage. It is proposed, not approved.
Verified . Report a correction
Last verified · How we report · Report a correction

- Source Briefing
- Public record
A 96MW data centre is proposed for Lucca Road, Wyong, on the Central Coast. The NSW Planning Portal lists it as state significant development SSD-148199991 at the “Prepare SEARs” step. For Sydney and NSW developers, it is another sign that data centre demand is moving beyond western Sydney into regional industrial precincts with grid access.
The proposal is not approved. The portal page does not name the applicant or a capital investment value. The Newcastle Herald reports the applicant is DCG Admin and puts the investment at $1.5 billion, citing the scoping report. We have not been able to confirm either detail from a public record.
The permits and deals moving Australia.
Free, every weekday.
Why it matters
Data centres are competing with logistics and manufacturing users for serviced industrial land. A project of this size on the Central Coast tests how much power the local network can give a single tenant.
The site sits beside an existing industrial development, inside the precinct the Herald calls North Wyong’s industrial and enterprise area. The Newcastle Herald reports the scoping report places it less than 1 km from Ausgrid’s 132 kV Wyong Zone Substation.
The scoping report says the site’s proximity to the Wyong Zone Substation allows “efficient connection to existing transmission infrastructure”, according to the Herald, without new transmission corridors.
For builders and contractors, a two-storey data centre of this scale would mean large civil, structural and electrical packages if it ever proceeds. Nothing has been tendered, and the record gives no construction timeline. Landowners and agents near the precinct should also watch how the proposal affects demand for large industrial lots.
The numbers
The Planning Portal describes the project as the operation of a data centre with a 96MW load capacity. It comprises one two-storey building, ancillary office space, car parking, landscaping and site works.
The Herald reports further figures from the scoping report. We have not verified these against the document:
- Capital investment of $1.5 billion.
- Total power consumption of about 150MW. The Herald gives 96MW as the target IT load, which matches the 96MW load capacity on the portal.
- A site of 12.43 hectares.
- 85 car parking spaces.
- Operation 24 hours a day.
- A dry, air-cooled design that uses no water for cooling, in line with NSW data centre guidelines.
The scoping report also flags flooding and easements on the site, and argues the project would still put industrial land that supports jobs to productive use.
Neither the Planning Portal page nor the Herald article gives a job count. We have not estimated one.
What’s next
The next step is the Secretary’s Environmental Assessment Requirements, known as SEARs. These set out what the applicant must study in its environmental impact statement.
After that, the stages on the portal are the EIS, public exhibition, submissions, response to submissions, assessment, recommendation and determination. As a state significant development, it will be decided through the NSW planning system rather than by Central Coast Council, which covers the site.
Flooding, easements and the local power connection are the issues most likely to draw scrutiny. The portal lists no key dates yet, so the timetable is open. Any approval would also depend on the grid operator agreeing to supply a load of this size, which the record does not address.
Our team will update this story when the SEARs are issued or the project page changes.
Readers tracking data centre activity can compare it with the Microsoft Huntingwood data centre, which has been approved.
Quick answers (2)
Quick answers
What are the key numbers in this story?
load capacity on the Planning Portal record: 96MW; state significant development number: SSD-148199991; current assessment stage: Prepare SEARs.
Where does this information come from?
This story cites NSW Planning Portal and Newcastle Herald, including the public record (NSW Planning Portal). Every source is linked on the page.
Sources and records (2)
On the record
The NSW Planning Portal lists Lucca Road Data Centre Wyong as SSD-148199991 at the Prepare SEARs stage, with a 96MW load capacity in the Central Coast local government area.
Public record · planningportal.nsw.gov.au
Also reported by
Filed by the AusDev Sydney Desk. How we report.
Next story · SydneyRandwick shoptop tower, 237 apartments, goes on exhibitionRead next →A state significant proposal for about 237 apartments in a 13-storey shoptop building at 73-109 Belmore Road, Randwick, is on exhibition to 11 December 2026.