Fri, 6 Nov 2026

Court grants consent for six-lot Glenwood subdivision

On 6 Nov the Land and Environment Court upheld an appeal and granted consent to turn one lot at 20 Ali Place, Glenwood, into six, after Blacktown refused it.

Illustration for: Court grants consent for six-lot Glenwood subdivision
Illustration. A representative image, not a photo of the site named in this story.
1 to 6lot split
6 Novconsent date

The NSW Land and Environment Court on Friday 6 November upheld an appeal against Blacktown City Council and granted consent to subdivide one lot at 20 Ali Place, Glenwood, into six residential lots. The decision, [2026] NSWLEC 1743, was made by Commissioner O’Neill after a conciliation conference held the same day.

Why it matters

The council had refused Development Application 25-02117, and the applicant appealed under section 8.7(1) of the Environmental Planning and Assessment Act 1979. The proposal involves knocking down the existing house and related structures, removing trees, splitting one lot into six under Torrens title, and building the roads and civil works that go with it. The site is Lot 2 in Deposited Plan 1142194.

The news that moved today. Free email. Every weekday morning.

The court arranged a conciliation conference under section 34 of the Land and Environment Court Act 1979. According to the judgment, the parties reached agreement on the terms of a decision, and the Commissioner was required to dispose of the proceedings in line with that agreement if it was a decision the court could have made.

We reported on 4 November that an appeal over a Hornsby project was upheld. The agreed outcome here involved the court using section 4.16 of the Act to grant consent. The judgment says this was an extemporaneous decision, delivered on the day.

The numbers

The judgment states the Council consented to an amendment of the application under section 38(1) of the Environmental Planning and Assessment Regulation 2021. The amended proposal finishes Poppy Way as a cul-de-sac; the original design had it running through to Ali Place.

The Council told the court it was satisfied that every contention in its Statement of Facts and Contentions, filed on 1 April 2026, was resolved by the amended application and the conditions of consent. The Commissioner therefore only needed to consider whether any provision in an environmental planning instrument limited the power to grant consent.

On that point, the Commissioner accepted the Council’s assessment that the site is suitable for the development. That rests on an environmental detailed site investigation dated 1 December 2025, prepared by KFM Geotech Pty Ltd, and the matters under section 4.6 of the State Environmental Planning Policy (Resilience and Hazards) 2021 were found to be satisfactorily addressed.

The site also sits in the Hawkesbury-Nepean Catchment, so the catchment rules in Chapter 6 of the Biodiversity and Conservation SEPP 2021 apply. According to the judgment, the Council assessed that the proposal would not lower the quality of water reaching a natural waterbody, and would come as near as possible to a neutral effect. That assessment rests on water quality targets, treatment through stormwater drainage easements and pits, and sediment and erosion control plans.

The judgment does not state a dwelling count, a construction cost or a sale value, so none is reported here.

What’s next

The orders are in three parts. First, the appeal is upheld. Second, consent is granted to DA 25-02117 as amended, on the conditions at Annexure A. Third, the applicant must pay the Council’s costs thrown away because of the amendment, as agreed or assessed, under section 8.15(3) of the Act. The judgment does not give a dollar figure for those costs.

Consent allows the subdivision and civil works to proceed within the approved conditions. The judgment does not set a start date or a lot release timetable.

Quick answers

What are the key numbers in this story?

lot split: 1 to 6; consent date: 6 Nov.

Where does this information come from?

This story cites NSW Land and Environment Court, including the public record (NSW Land and Environment Court). Every source is linked on the page.

On the record

The amended proposal ends Poppy Way in a cul-de-sac instead of a through road to Ali Place, and the court ordered the applicant to pay the council's costs thrown away by the amendment.

Public record · caselaw.nsw.gov.au