Shell's QGC urges council not to approve $32b data centre yet

Capital Brief reports nearly 600 objections were lodged, with QGC's submission among them and framed as constructive rather than opposed to data centres.

Verified . Report a correction

Last verified · How we report · Report a correction

Illustration for: Shell's QGC urges council not to approve $32b data centre yet
~600objections lodged
$32breported cost
1.4GWdata centre capacity

Queensland Gas Corporation (QGC), a Shell subsidiary, has urged Western Downs Regional Council not to approve Zerra DC’s proposed data centre until the developer guarantees its gas operations will not be affected, Capital Brief reported on 27 November 2026. Consultation on the application has closed. No council decision has been reported.

Why it matters

The project is a 1.4GW facility with a reported cost of $32 billion, set to be leased by Anthropic. Zerra DC, a first-time developer, leads a consortium backed by Macquarie Capital and Dexus, and Capital Brief says it is racing to have the facility running in 2027.

The permits and deals moving Australia.
Free, every weekday.

Edition: All markets.

Capital Brief says QGC has a “significant operational presence” in the area. It contrasts QGC with the many submissions based on templates from Lock the Gate Alliance and Western Downs Says Pause.

Shell also stressed that it does not oppose data centres in general, and Capital Brief quotes it as ready to cooperate with the developer. The outlet adds that QGC’s concerns add pressure on that 2027 timetable and show how hard it is to build in regional areas such as the Western Downs. Capital Brief reports QGC is open to talks with Zerra, the council and government agencies aimed at a result that works for all sides.

The numbers

Capital Brief reports nearly 600 objections reached Western Downs Regional Council before consultation closed. The project is reported at $32 billion and 1.4GW.

Capital Brief does not report what guarantee QGC wants, or how the council will treat the submission. It does not give a site address, and we have not read QGC’s submission or the council’s register. The report does not say whether the submission is formal grounds for refusal or a request for conditions.

What’s next

The council has to decide the application, and the report does not give a decision date. As we reported on 11 November, Zerra DC has named CPB as builder and has a first-pass Powerlink agreement covering the first of four buildings, but the development application was not approved.

For Brisbane developers and builders, the report shows an established gas operator can object to a large regional proposal. Checking for neighbouring gas operations is a sensible early step for any project in Western Downs.

Source: Capital Brief

Quick answers (3)

Quick answers

What is the latest on Digital Park?

Capital Brief reports nearly 600 objections were lodged, with QGC's submission among them and framed as constructive rather than opposed to data centres.

Which companies are named in the Digital Park story?

Zerra DC is named in this story, which cites Capital Brief.

What are the key numbers for Digital Park?

objections lodged: ~600; reported cost: $32b; data centre capacity: 1.4GW.

Sources and records (1)

On the record

Our 11 November story on Zerra DC naming CPB as builder shows the application was still unapproved by council; this report adds the gas-operator objection.

Our coverage · Read our earlier story

How we report →

Filed by the AusDev Queensland Desk. How we report.

Next story · QueenslandEumundi Holdings seeks minor change to approved Eumundi centreRead next →Eumundi Holdings filed on 19 November to have a revised Eumundi supermarket centre treated as a small tweak to its 2024 approval; next court date 10 December.