Abetz says $875m stadium cap 'technically' breached
Treasurer Eric Abetz told a committee the $875m state cap on the Macquarie Point stadium is 'technically' breached; cabinet is expected to decide 10-18 Dec.
Verified . Report a correction
Last verified · How we report · Report a correction

- Source Briefing
- Read original source · Pulse Tasmania
Treasurer Eric Abetz told parliament’s Public Accounts Committee on Friday 27 November that the Tasmanian government expects to build the Macquarie Point stadium in Hobart without any extra cash from Canberra, the AFL or Cricket Australia, according to Pulse Tasmania. Cabinet still has to make the call.
Why it matters
Pulse reports Abetz accepted that the $875 million ceiling on the state’s contribution has “technically” been broken, in the outlet’s wording. Last December Premier Jeremy Rockliff and Abetz put their names to a written pledge on that ceiling, later tabled in parliament.
The permits and deals moving Australia.
Free, every weekday.
Asked whether the stadium would proceed without extra money from partners, Abetz answered that this was his expectation. He said he could not yet say how far past the ceiling the state would go, and that the government would set that out once the final price is known.
Abetz attributed about $100 million of added cost to Middle East developments after 28 February. He also pointed to Townsville, where Pulse says the Commonwealth paid a third of the cost, and said a similar share for Hobart would help. On whether partners had answered requests for more money, he said only that the government had reached out.
Independent MLC Ruth Forrest, who chairs the committee, likened the arrangement to signing a blank cheque.
The numbers
Updated estimates released this week value the stadium by itself at $1.23 billion, a rise from the earlier $1.13 billion. Once the precinct works are added, along with the delivery costs of the Macquarie Point Development Corporation (MPDC), the total reaches $1.545 billion.
Kathrine Morgan-Wicks, who heads the Department of Premier and Cabinet, said the corporation is negotiating a fixed lump-sum price contract, and that value management has identified around $100 million in savings.
On the contract, Abetz said a Tasmanian Public Finance Corporation (TasCorp) funding facility would stand behind the MPDC board when it signs. Gary Swain, the Treasury secretary, said the facility was prepared to cover costs whether or not third parties contribute, but he said its maximum limit has not been set.
Labor’s Dean Winter credited crossbencher Bec Thomas with pressing for the ceiling, saying she saw cost growth coming.
What’s next
Pulse reports cabinet is expected to decide between 10 and 18 December, and the contract itself falling due on 18 December. Until then the size of any state contribution above $875 million, and the limit on the TasCorp facility, remain open.
Pulse adds that the government is aiming for the Devils to take the field there in 2031.
Source: Pulse Tasmania.
Quick answers (2)
Quick answers
What are the key numbers in this story?
state cap: $875m; contract date: 18 Dec; identified savings: $100m.
Where does this information come from?
This story cites Pulse Tasmania. Every source is linked on the page.
Sources and records (1)
Sources
Also reported by
Filed by the AusDev Tasmania Desk. How we report.
Next story · TasmaniaWest Coast Council report urges state cash; minister defersRead next →An unreleased expert report on West Coast Council's finances urges state support, The Advocate reported on 27 November. The minister defers to council.