Tasmanian Labor wants data centre freeze, backs $3,000 a MW fund

Labor's Josh Willie wants no new Tasmanian data centres or agreements until safeguards exist, two days after the government's final expectations.

Illustration for: Tasmanian Labor wants data centre freeze, backs $3,000 a MW fund
$3,000per MW
20MWsize threshold
6 monthsreview point

On Sunday 15 November, Tasmanian Labor’s Josh Willie called for no new data centres and no new agreements in the state until stronger safeguards are in place, Pulse Tasmania reported. The call came two days after the Tasmanian government released its final statement of expectations for data centres and AI infrastructure.

Why it matters

Labor’s position has hardened inside a week. Pulse Tasmania reported that Labor MLC Sarah Lovell said the previous Sunday that the party did not support a moratorium and wanted strong, enforceable guidelines and guardrails instead. Willie’s freeze goes further than that.

The news that moved today. Free email. Every weekday morning.

Willie said the government’s policy leaves Tasmanians worse off. Pulse Tasmania reported him arguing that data centres can switch on without new generation power, that there is no limit on their power and water use, and that the arrangements rest on secret deals. He also opposed letting proponents administer their own community funds.

The numbers

Pulse Tasmania said the policy sets a floor of $3,000 per megawatt each year, paid into a local community benefit fund, for any facility above 20 megawatts. Inside Local Government, summarising the government release, described the minimum as $3,000 per MW of contracted firm demand per year, with contributions starting once a centre is operating.

Pulse Tasmania also reported that developers must report their energy and water use every quarter. Inside Local Government said the expectations will be reviewed after six months, with further community consultation.

Premier Jeremy Rockliff defended the fund in the Pulse Tasmania report, calling it significant and saying a 100-megawatt data centre would pay around $300,000 a year.

What’s next

Willie said Labor would release its own expectations for data centres before the end of the year and would pursue the issue when parliament sits next week, according to Pulse Tasmania.

The government’s side, as reported by Pulse Tasmania, is that Labor lacks backbone on attracting investment and jobs, and that developers who cannot meet the requirements should look elsewhere. Rockliff described switching on before new generation exists as a transition while Tasmania brings Marinus Link online.

Inside Local Government reported that proponents must enter an agreement setting out project requirements, covering on-island renewable generation, accountability, transparency and opportunities for local businesses. Energy Minister Nick Duigan said developers will have to back their power needs with new renewable projects.

Earlier Tasmanian data centre coverage: Firmus Wesley Vale Road facility approved at Latrobe.

Quick answers

What are the key numbers in this story?

per MW: $3,000; size threshold: 20MW; review point: 6 months.

Where does this information come from?

This story cites Pulse Tasmania and Inside Local Government. Every source is linked on the page.