Where Melbourne's data centre projects stand in November
Three Melbourne data centre plans, each stuck on power, planning pathway or residents, with a state election on 28 November.

- Source Briefing
- Read original source · The Age
Melbourne’s data centre plans have run into the same wall from three directions: planning pathway, residents and power. This is where our own earlier reports leave three of them, ahead of the state election on 28 November.
Brooklyn: the queue and the deadline
The Age reported on 1 November that Planning Minister Sonya Kilkenny had until 6pm on 3 November to decide nine data centre proposals worth more than $5 billion, before caretaker conventions applied. All 79 Victorian councils had demanded a moratorium on 30 October. Stockland’s Brooklyn plan would convert a distribution centre into a data centre up to eight storeys tall, with stage one costing $935 million, across 22 hectares. Acoustic consultants found its 96 rooftop chillers need an 11-decibel noise reduction package, with houses as close as 170m. We have not found a published outcome for Brooklyn. See Victoria’s $5b data centre queue hits minister’s caretaker deadline.
The news that moved today. Free email. Every weekday morning.
Spotswood: residents against a fast-track permit
Information Age reported that residents are campaigning against Greensquare’s $1.47 billion, 240MW plan, as close as 100m from homes and a childcare centre. Greensquare refiled under the state’s fast-track pathway, which leaves objectors no VCAT appeal. The new rules, a 150m buffer from homes, schools and childcare centres plus a renewable energy requirement, are not retrospective. Reports that the proposal was withdrawn leave its status unclear. See Spotswood residents campaign against Greensquare’s $1.47b data centre.
West Footscray: M3 waits on power
NextDC chief executive Craig Scroggie apologised to residents on 9 November, Brisbane Times reported, but kept the plan to double M3 to about 10 hectares. Jemena paused its plan for 15-metre power poles in September after objections. NextDC’s October delay was followed by a 40 per cent share price drop, the outlet reported. The state has not approved the expansion, and no decision is expected before the election. See NextDC apologises to West Footscray over M3 power poles.
What to watch
- Whether the Brooklyn proposal is decided, or left to the next government.
- Whether the 150m buffer rules, expected from early 2027, reach projects already in the system.
- NextDC’s update once a power solution is contracted.
This is a status check on our earlier reporting, not new information.
Quick answers
What is the latest on Stockland?
Three Melbourne data centre plans, each stuck on power, planning pathway or residents, with a state election on 28 November.
What are the key numbers in this story?
proposals in the queue: 9; Spotswood proposal: $1.47b; planned M3 size: 10 ha.
Where does this information come from?
This story cites The Age, Information Age (ACS) and Brisbane Times. Every source is linked on the page.
On the record
Our three recent Melbourne data centre stories describe three different blockers: a ministerial decision deadline (Brooklyn), a fast-track permit with residents opposed (Spotswood) and a power connection (M3, West Footscray).
Our coverage · Read our earlier story
Also reported by
Filed by the AusDev Melbourne Desk. How we report.