SunLinQ wins The Wave Stage 2 design deal on the Sunshine Coast

The 7km twin-track section runs through a Little Mountain tunnel and adds two stations.

Last verified · How we report · Report a correction

Illustration for: SunLinQ wins The Wave Stage 2 design deal on the Sunshine Coast
7kmStage 2 length
2new stations
3,300jobs, Stages 1 and 2

On 18 November 2026 the Queensland Government named the SunLinQ consortium as the group to handle design and early works on the second stage of The Wave, the Sunshine Coast rail project. It did not disclose what the contract is worth.

Why it matters

Stage 2 is the Caloundra to Birtinya link, a new dual-track line of about 7km. It sits between Stage 1, from Beerwah to Caloundra, and the later stages heading towards Sunshine Coast Airport. For builders and suppliers in the region, the award names the group that will shape the detailed design and early works.

The news that moved today. Free email. Every weekday morning.

The consortium

SunLinQ is made up of four contractors:

  • BMD Constructions
  • CPB Contractors
  • GS Engineering and Construction Australia
  • UGL Engineering

What Stage 2 includes

The track passes under Little Mountain in a tunnel. Planners have pencilled in a pair of new stops, Aroona and Birtinya. Ground investigations are already running to feed the detailed design.

The numbers

  • Stage 1 funding: $550 million, shared between the state and federal governments.
  • Jobs: about 3,300 across Stages 1 and 2.
  • Stage 2 contract value: not disclosed.

Funding and timing

The government wants main works to begin in early 2027, once the federal environment approval comes through. Residents will be consulted on the station precincts at around the same time.

Funding for the later stages has not been finalised, and the statement says the federal government has not committed money to Stage 2. Transport Minister Brent Mickelberg said the state is “moving ahead” with a network meeting the region’s needs.

Source: Queensland Government statement, Sunshine Coast News.

Quick answers

What are the key numbers in this story?

Stage 2 length: 7km; new stations: 2; jobs, Stages 1 and 2: 3,300.

Where does this information come from?

This story cites Queensland Government statement (via Mirage News) and Sunshine Coast News. Every source is linked on the page.

Sources

Also reported by

How we report →

Filed by the AusDev Queensland Desk. How we report.