The Australian Developer
WED 09.30.2026CASH RATE 4.60%10-YR 5.340.02AUD US.69560.20%Newsletter

BESIX Watpac-John Holland JV Advances for Victoria Park Stadium

The Games authority has one consortium in the next round for the 2032 centrepiece, with the early contractor process to finish in the new year.

Edited by Sophie Nguyen · How we report
The Daily IndexEvery Brisbane deal, approval and collapse, in your inbox each morning.Get it free →
2027construction start
63,000seats, per ABC
70,000concert capacity
$7.1bGames Venues Infrastructure Program

The joint venture of BESIX Watpac and John Holland has moved to the next stage of the selection process to build Brisbane Stadium at Victoria Park, the Games Independent Infrastructure and Coordination Authority (GIICA) announced on 30 September. Construction is set to start in 2027.

The other shortlisted bidder, Australia’s Built in partnership with Sacyr, was named alongside it in April 2026. ABC News described the BESIX Watpac and John Holland team as the lone finalist; GIICA’s statement does not spell out what happens to the second bid.

Why it matters

GIICA describes the stadium as the city’s landmark venue for the 2032 Olympic and Paralympic Games. For the construction market, the decision signals which tier-one contractors are likely to draw on labour and supply chains in inner Brisbane from 2027.

Both firms have stadium records. GIICA cites BESIX Watpac’s work on Suncorp Stadium, the Gabba and Queensland Country Bank Stadium, and John Holland’s on the MCG Great Southern Stand, Marvel Stadium, Sydney Football Stadium and Penrith Stadium.

The Victoria Park site remains contested. ABC reports ongoing protests against building on the parkland.

The numbers

  • Capacity: 63,000 seats, per ABC, and a concert capacity of 70,000, per GIICA.
  • Cost: ABC reports $3.6 billion for the stadium. GIICA places it within the $7.1 billion Games Venues Infrastructure Program, jointly funded by the Australian and Queensland governments.
  • Timing: the early contractor involvement (ECI) process began in October 2025 and is to be finalised in the new year, with construction starting in 2027.

What’s next

During the ECI phase the joint venture works with GIICA to settle design detail and construction methodology. ABC reports contracts are expected in the new year. Subcontractors should watch for the JV’s package procurement once that contract is signed. More on the Brisbane Games pipeline, including the Bowen Hills PDA changes.

What we checked

What we checked ourselves, and where you can check it too.

  • Public recordGIICA's own announcement says the early contractor involvement process began in October last year, will be finalised in the new year, and that the stadium is part of the $7.1 billion Games Venues Infrastructure Program.View the record on giica.au

On the record

Primary recordGames Independent Infrastructure and Coordination AuthorityStadium specialists move to next stage of Brisbane Stadium selection process
Also reported by

Get tomorrow's Index

Every notable filing, deal, and approval in Australian development, ranked, in one three‑minute read each morning. Free.