Seymour Whyte, VSL, Arup win Barron River bridge contract at Kuranda
Detailed design runs over the next 12 months, and the state hopes for federal environmental approval by early 2028.
Last verified · How we report · Report a correction

- Source Briefing
- Public record
The Queensland Government said on 20 November that the design and construct contract for the new Barron River bridge on the Kennedy Highway at Kuranda (Far North Queensland) has gone to a joint venture of Seymour Whyte, VSL and Arup. Transport and Main Roads Minister Brent Mickelberg announced the award.
Why it matters
The bridge carries the Kennedy Highway between Cairns and the Tablelands. The release calls it a link for freight, tourism, businesses and local communities.
The approvals and deals moving Queensland. Free, every weekday.
For Queensland contractors, the award starts the supply chain for a regional crossing. The release says the next 12 months cover detailed design, further community consultation, site investigations and environmental assessments.
The new bridge will sit on a downstream alignment from the existing crossing. It will have wider traffic lanes and a separate path for walkers, bike riders and mobility devices. The release also lists better road approaches and a turnaround area at the top of Kuranda Range Road.
Mickelberg said the state hopes to have federal environmental approvals by early 2028 and would start construction soon after they arrive. He said the project has to protect the rainforest while still allowing construction to proceed. He did not give a start date for building.
Federal MP Matt Smith said the Australian Government is investing $245 million in the project. The release does not state a contract value or a total project cost.
Federal Infrastructure Minister Catherine King described the award as a milestone and said the design responds to the surrounding environment and reflects input from local suppliers.
Local MPs Bree James and David Kempton welcomed the start of detailed design. Kempton said the bridge had fallen into disrepair after maintenance was neglected over the past decade. Smith said the crossing is the gateway to the Tablelands and that better access could support growth in Kuranda.
Separately, the Queensland Audit Office has warned that Olympic builds will compete with hospitals and rail for workers, as covered in our earlier report.
The numbers
- $245 million Australian Government investment, per Matt Smith in the release.
- 12 months of detailed design, consultation, site investigations and environmental assessments, per the release.
- Early 2028 target for federal environmental approvals, per Mickelberg.
What’s next
Detailed design starts first, and building waits on the federal environmental approvals. The release does not give a completion date.
Quick answers
What are the key numbers in this story?
Federal funding: $245m; Design phase: 12 months; Approvals target: 2028.
Where does this information come from?
This story cites Queensland Government ministerial statement, 20 November 2026, including the public record (Queensland Government ministerial statement, 20 November 2026). Every source is linked on the page.
On the record
Contract awarded to design and construct new Barron River bridge
Queensland Government ministerial statement, 20 November 2026 · statements.qld.gov.au
Filed by the AusDev Queensland Desk. How we report.