Subiaco civic centre priced at $63.5m, Rankin Gardens left out

City of Subiaco officers recommend detailed designs for a $63.5m civic building at 241 Rokeby Road, with Rankin Gardens excluded. Council votes 24 November.

Last verified · How we report · Report a correction

Illustration for: Subiaco civic centre priced at $63.5m, Rankin Gardens left out
$63.5mproject cost
1,873petition signatures
$1.8mspent since 2020

PerthNow’s Western Suburbs Weekly reports that, before the City of Subiaco meets on 24 November, officers are urging councillors to advance detailed design of a new civic building and hub for the community at 241 Rokeby Road. The Lyons concept now being recommended keeps Rankin Gardens outside the project boundary.

Why it matters

It would replace the current civic building, which PerthNow says has been out of use since a roof fire in September 2022. Council offices, chambers and community services would share one building, with an exhibition space and a pavilion, plus parking.

The approvals and deals moving Perth. Free, every weekday.

The recommendation only advances the project to detailed design. No final budget is set, and construction tenders are advertised only after a further report to council.

The numbers

PerthNow puts the cost of the new council building at $63.5 million. As the outlet describes the officers’ report, trimming the landscaping would cut roughly $1 million. The link to the library and the upgrades along Rokeby Road stay in.

Since 2020 the city has spent about $1.8 million on architects and consultants, not counting staff time, PerthNow says.

Opposition has been sizeable. Two petitions against parts of the plan gathered 1,873 signatures combined, and 1,284 of those were on a petition to stop redevelopment of Rankin Gardens. Residents worried about losing open space, established trees and the gardens’ historic feel. Consultation feedback was mixed, with cost and building size also raised.

The officers’ report says major trees such as a bottle tree and some Norfolk Island pines would be retained, with extra shaded seating and spots for quiet recreation.

What’s next

PerthNow reports councillors are due to vote on the recommendation on 24 November. If it passes, detailed design proceeds. Before any construction tender goes out, a further report would come back to council covering an updated cost plan, the procurement approach, project management and a proposed maximum capital budget.

Councillors are not settling the project’s final cost at this stage. PerthNow also notes that leaving Rankin Gardens out is not a permanent guarantee, since further landscaping work is still to be considered.

Western Suburbs Weekly credits Lyons as the designer behind the concept images and the recommended detailed designs.

For another recent WA public-site redevelopment, see our report on the East Perth girls school site.

Quick answers

What are the key numbers in this story?

project cost: $63.5m; petition signatures: 1,873; spent since 2020: $1.8m.

Where does this information come from?

This story cites PerthNow, Western Suburbs Weekly. Every source is linked on the page.

Sources

How we report →

Filed by the AusDev Perth Desk. How we report.