WA commits $54.8m wastewater works for 3,500 Treeby, Jandakot lots
The WA Government said on 18 November it is spending $54.8m on wastewater works to service about 3,500 lots across 252 hectares in Treeby and Jandakot.

- Source Briefing
- Public record
The Western Australian Government announced on 18 November that it will fund $54.8 million of wastewater infrastructure in Perth’s south, aimed at servicing new housing in the suburbs of Treeby and Jandakot.
Why it matters
Sewerage capacity decides when land can be built on, and the statement ties these works to about 3,500 residential lots. The area covers 252 hectares east of Solomon Road, between Jandakot Road and Armadale Road.
The news that moved today. Free email. Every weekday morning.
The government also said Treeby’s population is forecast to grow about 68 per cent, to more than 12,300 people, over the next 20 years. The $54.8 million forms part of what it described as a $2.7 billion state-wide investment in water, wastewater and drainage.
Water Minister Daniel Pastorelli and Housing and Works Minister John Carey were both quoted in the release, along with Jandakot MLA Stephen Pratt. Pastorelli said the project is designed to minimise community and environmental disruption. Carey linked the works to housing supply and cited a record $10.8 billion housing investment.
The numbers
The statement lists three parts to the works:
- A mechanical and electrical upgrade of the Clementine Boulevard wastewater pump station, which will more than triple its pumping capacity.
- More than 5 km of new wastewater pipeline, with most of the pipe manufactured in Maddington.
- Micro-tunnelling beneath road, rail and freeway corridors, which the government said reduces disturbance in Beeliar Regional Park and protects native wildlife, including freshwater turtles.
Delivery is by a joint venture between DMCivil and tunnelling specialist Rob Carr. The statement says the works support 60 local jobs during construction.
The release says the micro-tunnelling approach was chosen to limit disturbance in Beeliar Regional Park, and that the Clementine Boulevard pump station upgrade is mechanical and electrical. Pastorelli’s comments framed the project as one designed to keep community and environmental disruption low, while Carey’s tied it to the state’s housing supply push.
What’s next
Wastewater capacity has been a recurring constraint on Perth housing, as in our earlier report on a $105m Perth wastewater upgrade clearing capacity for up to 60,000 homes.
The statement as published does not give a start date, a completion date or a breakdown of which lots are released first, so those remain open. It names no private developer and does not say which landholders’ lots are covered.
Quick answers
What are the key numbers in this story?
wastewater works: $54.8m; lots serviced: 3,500; catchment: 252 ha.
Where does this information come from?
This story cites Government of Western Australia, including the public record (Government of Western Australia). Every source is linked on the page.
On the record
We read the 18 November 2026 WA Government media statement: $54.8m of wastewater works to service about 3,500 lots across 252 hectares in Treeby and Jandakot, delivered by a DMCivil and Rob Carr joint venture.