Tasmania paid Veolia A$1.79m to end Macquarie Point power plan
ABC reported on 6 November that Tasmania paid Veolia A$1,788,236.50 plus GST on 24 June to end a planned thermal plant at Macquarie Point.

- Source Briefing
- Read original source · ABC News
The Tasmanian government paid Veolia a final invoice of A$1,788,236.50 plus GST on 24 June 2026 to end a planned thermal energy plant at Macquarie Point, Hobart (Southern Tasmania), ABC News reported on 6 November. The figures came from a letter Minister Eric Abetz sent to Greens Deputy Leader Vica Bayley, according to ABC.
Why it matters
Veolia had signed an agreement with the Macquarie Point Development Corporation to deliver a District Energy Infrastructure Scheme, which included the thermal plant. ABC reports the government has now paid to unwind it, and that Abetz says the payment is not included in the stadium’s A$1.13 billion budget.
The news that moved today. Free email. Every weekday morning.
Abetz told Bayley the scheme predated any stadium discussions and is not part of the stadium project, ABC reported. He described connecting to the existing electricity network as “lower risk and cost” than the thermal plant. Bayley, for the Greens, called the stadium a slow-moving train wreck and accused the government of wilful disregard for taxpayers’ money, ABC said.
The disclosure follows other exit costs at the precinct. ABC lists A$1.257 million paid to property developer Milieu to abandon its Escarpment housing project and A$1.84 million paid to Hobart Brewing Company to end its 10 year lease of The Goods Shed. It also notes an unsuccessful stadium construction tender bidder, not named in the report, was reimbursed A$2 million for its costs, up from an original cap of A$250,000, which ABC covered the previous week.
The numbers
Beyond the Veolia invoice, ABC reports a further A$667,407 went to Melbourne-based Renewable Intelligence for earlier work on the project.
The stadium is planned as a 23,000 seat venue on a 9.3 hectare waterfront site, and the government is in final negotiations with BESIX Watpac as builder, ABC said. The A$1.13 billion price is widely expected to rise because of inflation linked to the Middle East war, according to the report. Premier Jeremy Rockliff would not repeat his commitment to cap the state’s contribution at A$875 million, ABC reported, though ABC says he has promised to publish the cost before the final contract is signed. Earlier coverage of the builder choice is in our report on BESIX Watpac.
What’s next
Power for the precinct is now planned as a connection from the North Hobart substation using existing network capacity, ABC reported. The connection cost is still being finalised with TasNetworks and is not in current estimates, according to Abetz.
ABC notes TasNetworks earlier told the development corporation the precinct needs 15.7 megavolt-amperes, above existing network capacity, while Abetz told a budget estimates committee the figure was 9.7 megavolt-amperes. That gap remains unresolved in the report.
Two decisions are due: the builder negotiations with BESIX Watpac need to conclude, and the government has said the stadium cost will be released before the construction contract is signed.
Quick answers
What is the latest on Veolia?
ABC reported on 6 November that Tasmania paid Veolia A$1,788,236.50 plus GST on 24 June to end a planned thermal plant at Macquarie Point.
What are the key numbers in this story?
Veolia invoice: A$1.79m; consultant payment: A$667,407; stadium budget: A$1.13b.