Burnie foreshore redevelopment: $3.8m project due Dec 2027
Burnie City Council lists its foreshore redevelopment at $3.8 million inside a $17.3 million urban plan, with completion planned for 31 December 2027.

- Source Briefing
- Public record
Burnie City Council is upgrading the Burnie foreshore precinct in a $3.8 million project, according to the council’s July 2026 project update. A Pulse Tasmania Instagram post is headlined as the council releasing first images of the redevelopment; The Australian Developer could not open the post, so nothing else is taken from it.
Why it matters
The foreshore work is part of the Burnie City Centre Urban Plan, which the council’s project page puts at $17.3 million. The foreshore project is listed within it at $3.8 million.
The news that moved today. Free email. Every weekday morning.
The council says Tasmanian Government money pays for the project, as part of the state’s contribution to the urban plan. For a regional centre on the north-west coast, the project is meant to open up the waterfront.
According to the council’s July 2026 update, taking out the rail corridor will open up more community space. The project also brings upgraded playgrounds, outdoor recreation facilities and better cycling and running links.
The numbers
The council’s project page lists the Foreshore Redevelopment Project at $3.8 million, inside the $17.3 million urban plan. Planned completion is 31 December 2027.
On progress, the council reports that playground equipment has been ordered, with the fenced playground and an expanded outdoor gym still being designed. The council has also hired a design consultant to produce detailed designs and tender documents. Playground installation is scheduled for early 2027.
The council says development approval has been received for rail corridor removal. A Ministerial application under the Strategic Infrastructure Corridors Act was submitted in July 2026. The council adds that contractor expressions of interest are to be sought for rail infrastructure removal, subject to approval.
What’s next
On the same coast, see also TasTAFE’s Burnie accommodation opening.
Rail corridor removal is the step that depends on approval. The council’s page says expressions of interest from contractors will be sought once that approval is in place, so the Ministerial decision under the Strategic Infrastructure Corridors Act is the next gate to watch.
The council’s timeline then runs to playground installation in early 2027 and overall completion on 31 December 2027. The consultant’s detailed designs and tender documents will show more of the final layout.
The council’s page is the July 2026 update, so figures and dates may have moved since.
The Australian Developer
Quick answers
What are the key numbers in this story?
project budget: $3.8m; urban plan: $17.3m; planned completion: Dec 2027.
Where does this information come from?
This story cites Pulse Tasmania (Instagram) and Burnie City Council, including the public record (Burnie City Council). Every source is linked on the page.
On the record
The council's July 2026 project update lists the Foreshore Redevelopment Project at $3.8 million with planned completion on 31 December 2027.
Public record · burnie.tas.gov.au