Kogarah Bay 25-unit block ordered to fix four serious defects

Building Commission NSW issued a rectification order on 30 Oct for 2-6 Lacey Street, Kogarah Bay, covering four serious defects with a three-month deadline.

Last verified · How we report · Report a correction

Illustration for: Kogarah Bay 25-unit block ordered to fix four serious defects
4serious defects
25apartments
3 monthscompliance period

Building Commission NSW issued a building work rectification order on Friday 30 October 2026 against Settlers Kogarah Bay Development Pty Ltd, the developer of a seven-storey apartment building at 2-6 Lacey Street, Kogarah Bay, in Sydney’s south. The order says the company must carry out building work to remediate the serious defects listed in it within three months.

Why it matters

The order is published on the Building Commission NSW register of building work orders. It was issued under section 33 of the 2020 RAB Act, the state’s apartment compliance law. The order describes the building as a Class 2 residential apartment building, strata plan SP 109579, with 25 units and two levels of basement car park. It says work was authorised to start on 21 February 2022.

The news that moved today. Free email. Every weekday morning.

The order records that Jason Li, Director, Building Compliance at Building Commission NSW, formed a “reasonable belief” that the building has a serious defect. It states he relied on an inspection by authorised officers of the Department of Customer Service on 30 June 2026. A copy of the inspection report was provided to the developer on 13 July 2026, according to the statement of reasons attached to the order.

The order names Settlers Kogarah Bay Development Pty Ltd (ACN 645 748 189) as both the developer and the principal contractor. A rectification order is a regulatory step. It is not a finding on anything beyond what the order itself records.

The numbers

Table 1 of the order lists four serious defects and the location of each.

  1. An external concrete slab and enclosure supporting the brigade booster assembly. The order describes differential settlement on the northern edge, an estimated 100 mm level difference between the southern and northern ends, staining on the Level B1 shotcrete wall, and apparent voids beneath sections of the slab.
  2. Water penetration from an external wall, window or roof in Units 403 and 404 and typical apartments.
  3. Retained water, ponding or inadequate falls on a roof or external pebbled area, again in Units 403, 404 and typical apartments.
  4. Unprotected services penetrations in the main switch board room and service risers, in a wall, floor or ceiling required to have a fire resistance level. The order says the installation does not match those of a tested system.

For defects 2 to 4 the order requires inspections to identify all locations of the defect, then a written report and designs, then the rectification work. The report and designs are due within one month, the work within a further two months, a total of three months from 30 October.

The statement of reasons also lists the developer’s contact with the Commission before the order. A notice of the proposed order was given on 4 September 2026. The record lists written updates from the developer on 25 and 28 September and 1, 16, 22 and 23 October. It says the 16 October update had no information on completion of works, that no progress was made on site as at 22 October, and that no program was received by close of business on 26 October after the Commission asked for completion dates.

What’s next

The order takes effect from 30 October 2026 and remains in force until the Secretary revokes it. It carries a warning on the consequences of non-compliance, and says the developer must make good any consequential damage caused by the works.

Written reports must be prepared by a registered design practitioner under the Design and Building Practitioners Act 2020 and emailed to the Commission’s occupation certificate audits team. Designs must also comply with that Act.

The register page and PDF give no repair cost, no figure for affected owners and no comment from the developer, and we have not stated any. The Commission’s earlier register entries are covered in our October roundup of rectification orders.

Source: Building Commission NSW register, order dated 30 October 2026. The Australian Developer.

Quick answers

What are the key numbers in this story?

serious defects: 4; apartments: 25; compliance period: 3 months.

Where does this information come from?

This story cites Building Commission NSW and Building Commission NSW (order PDF), including the public record (Building Commission NSW and Building Commission NSW (order PDF)). Every source is linked on the page.

On the record

The order lists four serious defects at 2-6 Lacey Street, Kogarah Bay, each with a one-month and a two-month stage, totalling three months from 30 October 2026.

Public record · nsw.gov.au

How we report →

Filed by the AusDev Sydney Desk. How we report.