Thu, 19 Nov 2026

Two Hunter data centres modelled at 6.2m tonnes of pollution a year

A Climate Council report models two proposed Hunter data centres at 3.1 million tonnes of pollution each a year by 2035, the Newcastle Herald reports.

Illustration for: Two Hunter data centres modelled at 6.2m tonnes of pollution a year
6.2mtonnes a year
1GWeach campus
$10bMayfield precinct

Two data centre campuses planned for the NSW Hunter could together emit about 6.2 million tonnes of carbon a year by 2035 unless new renewable supply is built alongside them, the Newcastle Herald reported on 19 November. For Hunter developers and power suppliers, the report points to tighter grid-matching rules ahead.

Why it matters

The analysis is titled Pollution Pipeline: Australia’s Dirtiest Data Centres and was written by the Climate Council and the Carbon Zero Initiative. The Herald says it places Voltic DC’s Warkworth proposal and the Mayfield precinct, near Denman, in a national top nine of high-emission data centre plans.

The news that moved today. Free email. Every weekday morning.

Both sites are modelled at 3.1 million tonnes annually in 2035. That assumes they take power from the existing grid, with no new solar, wind or storage built to cover their load, and average half of full capacity. The report calls its power station comparison “illustrative only” because the years and methods differ.

Four of the nine plans are in NSW. The Herald says the two Hunter sites make up about 6.2 million of the state’s modelled 10.2 million tonnes.

The numbers

  • Voltic DC’s Hunter Valley AI Training Campus is planned at up to 1 gigawatt, next to the Redbank Power Station at Warkworth.
  • Mayfield is a joint plan by Malabar Resources and Akaysha Energy for up to 1 gigawatt of IT load, alongside Malabar’s mining sites in the Muswellbrook local government area. A battery of as much as 2 gigawatts, storing 8 gigawatt hours, is part of the plan.
  • Akaysha has earlier put Mayfield’s cost at up to $10 billion.
  • Eraring, the country’s largest coal-fired plant, reported 13.5 million tonnes in 2024-25. The Herald notes the two Hunter sites add up to almost half of that on the report’s figures.
  • The report puts all nine proposals at 40 million tonnes a year.

The Herald says the report cites Baringa modelling for the Clean Energy Finance Corporation. That modelling has wholesale power prices up 20 per cent across the main grid by 2035 without matching renewables and storage, and 26 per cent in NSW. The report also says the queue of data centres seeking a grid connection has more than doubled in a year, to 225.

What’s next

The Herald says Voltic’s campus would take grid power. Redbank’s owner, Verdant Earth Technologies, wants to turn the former coal station into a biomass burner, which the NSW Independent Planning Commission rejected in 2025. Voltic says it would look at supply deals with Verdant if that plan proceeds.

For another NSW campus, see our earlier report on NEXTDC’s Horsley Park expansion. An environmental impact statement for Mayfield is due in the first half of 2027.

The Climate Council wants Canberra to close gaps in its planned national standards, which the Herald says the government aims to legislate in early 2027. It asks that the rules cover every facility above 30 megawatts starting operation after 23 March 2026, force new renewables and storage to match demand, exclude gas as a main supply and bar drinking water for cooling in water-stressed regions. The Herald adds that NSW guidelines already offer faster assessment to projects that match demand with new renewables within four years, but the report says they are voluntary.

The report also counts 43.6 gigawatts of approved renewable projects with no buyer yet, and says solar has averaged 21 months and wind 30 months from investment decision to operation since 2017.

These are modelled estimates relayed by the Newcastle Herald, not approvals or measured emissions. The Australian Developer has not independently verified the modelling.

Quick answers

What is the latest on Voltic DC?

A Climate Council report models two proposed Hunter data centres at 3.1 million tonnes of pollution each a year by 2035, the Newcastle Herald reports.

What are the key numbers in this story?

tonnes a year: 6.2m; each campus: 1GW; Mayfield precinct: $10b.

Where does this information come from?

This story cites Newcastle Herald. Every source is linked on the page.

Sources

How we report →

Filed by the AusDev Sydney Desk. How we report.