Brisbane building costs to climb 10% in 2028, WT warns

WT's latest market conditions report says a slowdown would bring only short-lived relief, with south-east Queensland under the most pressure.

Last verified · How we report · Report a correction

Brisbane building costs to climb 10% in 2028, WT warns
The Australian Developer
10.0%Brisbane building escalation, 2028
6.0%national building escalation, 2028
8.5%Brisbane average a year, 2027-29
  • Source Briefing
  • Public record

Building costs in Brisbane are forecast to rise 10.0% in 2028, the steepest of any market in the country, according to the November 2026 Australian Construction Market Conditions Report from project advisory firm WT.

The report, released on 19 November, says construction cost escalation across Australia will stay above average through to 2029, even with an elevated risk of an economic slowdown.

The news that moved today. Free email. Every weekday morning.

Why it matters

The release says federal tax changes and higher interest rates are weighing on residential construction even as the underlying need for new housing keeps growing. Roast said the shortfall is not going away, and that when efforts to address it ramp up they will land on a sector that is already stretched.

The numbers

WT forecasts national building escalation of 5.5% in 2027, rising to 6.0% in 2028 and easing to 5.6% in 2029. Infrastructure escalation is tipped to climb steadily from 5.0% in 2027 to 5.7% in 2029, which would take it past building by the end of the period.

WT Construction Economist Damon Roast said in the release that activity should stay strong in many sectors despite higher interest rates, elevated oil prices and the risk of an AI investment bubble bursting. If those risks do hit, some projects could be paused and costs could ease for a while, he said, but “unless it turns into a deep downturn, that relief will be short-lived.”

Roast’s argument is that pressure returns, potentially stronger, once activity picks up, because the sector tends to stop investing in its own capacity and productivity during weaker periods.

Brisbane is the most pressured market in the report, with building escalation forecast to average 8.5% a year from 2027 to 2029. The Sunshine Coast (9.6%) and Gold Coast (9.5%) sit close behind in 2028, and WT says pressure is spreading beyond the south-east, with Cairns facing infrastructure escalation of 8.0% in 2027.

Elsewhere, WT forecasts Perth building escalation averaging 6.1% a year over 2027 to 2029 and Adelaide 5.7%. Melbourne is set for a belated uplift averaging 4.8%, while Sydney is forecast at 4.6%.

What’s next

WT National Director James Ford said clients should plan for sustained cost pressure rather than wait for a slowdown to bring prices down. In his view, those who build realistic escalation allowances into their plans, lock in scope early and match procurement to current conditions will be better placed than those who hold off.

The report also notes that construction productivity has been weak for many years, and that more investment in technology and wider industry adoption could lift capability and ease cost pressure over the longer term.

WT says its 2026 and 2027 business-as-usual forecasts exclude the direct cost impacts of the Middle East conflict, which vary widely by project type. The full report is available on WT’s website.

Quick answers

What are the key numbers in this story?

Brisbane building escalation, 2028: 10.0%; national building escalation, 2028: 6.0%; Brisbane average a year, 2027-29: 8.5%.

Where does this information come from?

This story cites WT (media release). Every source is linked on the page.

On the record

WT media release on its November 2026 Australian Construction Market Conditions Report, supplied to the desk under embargo.

Public record

Company announcement

How we report →

Filed by the AusDev Queensland Desk. How we report.

Newsletter

Get the Queensland Daily Index

One free briefing every weekday morning.