Light Rail 2A track slab 100% complete, lyric theatre tops out 2027
ACT Government says Light Rail Stage 2A track slab is complete, the lyric theatre tops out early 2027 and 744 piles are in at UNSW Canberra City.

- Source Briefing
- Public record
The ACT Government said on 28 October 2026 that the track slab for Light Rail Stage 2A in Canberra’s City Centre is 100 per cent complete, in a joint release from Chief Minister Andrew Barr and Minister Chris Steel that also reported progress on the new lyric theatre and the first stage of the UNSW Canberra City campus.
Why it matters
The release groups three city-shaping projects in the one update, alongside the Canberra Aquatic Centre and the National Convention and Entertainment Centre, which it says the Government is also progressing. Per the release, the works are part of the largest transformation in the City Centre’s history.
The news that moved today. Free email. Every weekday morning.
The track slab milestone follows 18 months of works in London Circuit East. The Government says the Light Rail construction compound in the Theatre Lane car park is now being dismantled so the area can return as public parking.
For the lyric theatre, the release says Multiplex will install structural steel and begin façade works at the start of 2027. The Government says the venue will have a larger capacity than the existing theatres at the Canberra Theatre Centre, which it says will allow Canberra to host major musicals, ballet, opera and touring acts that currently cannot come to the city.
The numbers
- Light Rail Stage 2A: 100 per cent of the track slab complete after 18 months of works in London Circuit East.
- Theatre Lane car park: 57 bays, including 8 accessible spaces, reopen from 31 October 2026, zoned for 2-hour use and free after 5.30pm from Wednesday to Sunday evenings.
- Light Rail stops: works on the three new stops are complete, with columns and canopies in place and platform fit-out under way.
- UNSW Canberra City: roughly 70,000 tonnes of material excavated and removed, and 744 piles installed to support the two new buildings at the corner of Constitution Avenue and Coranderrk Street.
The release also says London Circuit East is planned to partially reopen to traffic shortly after the car park reopens. Drivers and cyclists would be able to travel past Theatre Lane and turn left onto Northbourne Avenue, for the first time since the road closed in early 2025.
What’s next
On Light Rail, the release says scaffolding at the City South and Commonwealth Park stops will begin coming down in the coming weeks, and an artwork by local artist Hannah Quinlivan is due for the Edinburgh Avenue stop later this year. The project is described as on track to complete construction in the first half of 2027, with testing and commissioning leading to passenger services in 2028.
On the lyric theatre, the structure is on track to top out in early 2027. Construction then moves to fit-out through 2027, covering seating, stage infrastructure and specialist technical systems, with completion scheduled for mid-2028. For the venue’s wider visitor-economy projections, see the convention centre and lyric theatre pipeline story.
At UNSW Canberra City, a crane is due on site in November and the first basement concrete pour is planned before the end of 2026. The new facilities are on track for completion in 2028. UNSW is operating from the former Canberra Institute of Technology site in Reid in the meantime.
All dates and progress claims above are the ACT Government’s own, drawn from its release.
Quick answers
What is the latest on Multiplex?
ACT Government says Light Rail Stage 2A track slab is complete, the lyric theatre tops out early 2027 and 744 piles are in at UNSW Canberra City.
What are the key numbers in this story?
track slab: 100%; piles installed: 744; parking bays: 57.
Where does this information come from?
This story cites ACT Government (Barr and Steel joint media release), including the public record (ACT Government (Barr and Steel joint media release)). Every source is linked on the page.
On the record
Delivering on our plan: major progress across city-shaping projects, 28 Oct 2026
ACT Government (Barr and Steel joint media release) · cmtedd.act.gov.au
Filed by the AusDev Canberra Desk. How we report.