Gungahlin Town Centre East land release slips to 2027-28
A response to a question on notice, published on 16 November, moves the precinct's planned 2,500 homes back two years, and the subdivision design application is not yet lodged.

Land in Gungahlin Town Centre East is now forecast for release in 2027-28, according to an answer from Chief Minister Andrew Barr to a question on notice, made public on Monday 16 November. The outlet says that is two years after the government first expected.
Why it matters
The 32-hectare precinct is the last big undeveloped part of the Gungahlin town centre, per Canberra Daily. Plans call for 2,500 homes, among them affordable and build-to-rent, plus businesses and community spaces.
The news that moved today. Free email. Every weekday morning.
The Suburban Land Agency has consulted residents on a vision for the precinct, and the Territory Planning Authority must still assess and approve a subdivision design application.
Independent MLA Leanne Castley accuses the ACT Government of neglecting Canberra’s north, and doubts the new dates will hold, saying “I don’t have much faith in the Government’s forecasts”, as quoted by the outlet.
The numbers
The timetable has moved as follows, per Canberra Daily.
- April 2024: release was expected in 2025-26.
- March 2026: Mr Barr told the Legislative Assembly the application was finalised for lodgement in mid-2026, with staged releases from 2026-27.
- Barr’s latest answer: lodgement slides to the last quarter of FY2026-27, and the release to 2027-28.
Separately, the June 2026 land release program had pencilled in two residential and commercial sites here for this financial year, the outlet notes.
What’s next
The next marker is lodgement of the subdivision design application, then assessment by the Territory Planning Authority.
An ACT Government spokesperson said a project of this scale needs detailed planning, design and infrastructure coordination, and that the aim is to avoid rushing. The spokesperson added that significant work has gone into the application and that dates will keep being refined.
The government did not specifically explain the reason for the delay, the outlet says.
The timing matters for anyone tracking the Territory’s pipeline of residential and mixed-use land in the north. The Territory Planning Authority must approve the subdivision design before development can proceed, and the June 2026 program had pointed to releases this financial year. For another Territory project at an early stage, see the early designs for the new north Canberra hospital, which is also open for public feedback.
Quick answers
What are the key numbers in this story?
Precinct area: 32 ha; Planned homes: 2,500; Release year: 2027-28.
Where does this information come from?
This story cites Canberra Daily (Nicholas Fuller), 17 Nov 2026. Every source is linked on the page.